The biggest challenge with this project was maintain the pre-war charm of the space while still adding all the modern amenities we expect in a home today.
For example, when working with the HVAC company to install split system heating and cooling through, we had to adjust the original millwork locations to accommodate a required PTAC unit.
We also needed to install a new fireplace on top of the existing one. This required us to adjust the location of the flue and depth of the unit itself several times for a perfect fit. All in all, we were able to adjust our plans (ever so slightly) to ensure all the client’s needs and desires for the space were fulfilled.